|
1. General
2. Environment
3. Social
4. Public Environmental Report Process
5. Test Pit Southern Expansion
6. PER Lodgement Announcement
7. MRM Community Benefits Trust (pdf)
1. General Questions
What is proposed?
Xstrata Zinc has announced its intention to convert the underground zinc-lead
mine at McArthur River to an open cut operation to enable the mine to
continue production. The conversion to an open pit mine will extend the
mine's life by 25 years and entails an investment of AUD66 million. The
McArthur River ore body remains one of the largest deposits of zinc and
lead in the world.
The conversion will mean that a surface pit covering 83 hectares will
be constructed to access the ore, instead of accessing the orebody from
MRM's extensive network of underground tunnels and rooms.
The development of open pit mining within the existing mine lease will
necessitate the rechannelling of a 5.5 kilometre section of the McArthur
River and about 2.5 kilometres of Barney and Surprise Creek around the
open pit. No additional infrastructure will be constructed at the site.
The rechannelling will be undertaken as a detailed environmental project
over a two year period to encourage revegetation, minimise the loss of
biodiversity, and avoid any impact on downstream fishing activities. See
the Environment section for further information
on the environmental impact of the proposed change in mining method at
MRM.
The conversion of MRM to an open pit operation is dependent on approval
by the Northern Territory government. An environmental and social impact
study (EIS) was lodged in August 2005 for public review and comment and
a supplementary EIS was lodged in December 2005.
What is the timeframe for the proposed conversion to open cut mining?
Subject to the necessary approvals and the successful completion of the
environmental review process, construction would take around two years.
The actual timing depends upon if and when approval is granted and the
ability to schedule civil works around the wet seasons.
What will happen to McArthur River Mine if the proposed open cut operation
is not approved?
MRM has made considerable progress in the last 18 months in reducing
costs and improving the quality and commercial attractiveness of its bulk
concentrate product, particularly through the reduction of its silica
content. Despite these efforts, the mine in its current form has come
to the end of its effective economic life. The most accessible underground
ore has been extracted and the underground mining operations, which comprise
over 100 kilometres of underground tunnels, are no longer financially
viable.
If the proposal to convert MRM into an open pit mine is not approved,
the underground operation will close and the mine will be rehabilitated
in line with MRM's approved closure plan.
How does Xstrata's proposal differ from previous plans by the mine's
former owner, MIM, to expand the operation?
The open cut development marks a considerable change from previous plans
by the former MIM Holdings to expand the mine significantly, which entailed
the construction of a zinc refinery and coal-fired power station on site
and the damming of the Glyde River. The development of open pit mining
within the existing mine lease will necessitate the rechannelling of the
McArthur River but entails no additional infrastructure construction.
The rechannelling will be undertaken as a detailed environmental project
over a two year period to encourage revegetation and minimise the loss
of biodiversity, and to avoid any impact on downstream fishing activities.
Are there still long-term plans to establish a refinery and expand the
mine's operations?
Xstrata Zinc retains the option to develop MRM as a source of zinc feed
for a future zinc refinery using the Group's Albion process technology,
which would significantly improve the profitability of MRM's mining operations.
Given the power requirements associated with zinc refineries, the MRM
site has been ruled out as a possible location for an Albion plant and
we continue to assess other potential sites.
What changes are expected from a shift from underground to open cut mining?
The current mine occupies about 12 square kilometres. The change to open
pit operations will double this area to about 24 square kilometres. Other
changes are:
-
An 83 hectare open pit will be created by removal of surface material
and mining excavation operations.
-
About 5.5 kilometres of the McArthur River will be rechannelled,
partly into an old water course, to allow the river to flow around
the open pit.
-
About 2.5 kilometres of both Barney and Surprise Creeks will be rechannelled
around the open pit.
-
A flood protection bund will be built around the pit and facilities
as protection against flooding which sometimes occurs in the wet season.
-
A 300 hectare engineered overburden emplacement facility will be
constructed to store and control waste rock produced from open pit
mining.
-
Wastes from the processing facility (tailings) will be treated in
a significantly upgraded tailings facility.
-
New haul roads and a run of mine storage area will be built to transport
and store ore prior to processing.
MRM expected to start civil works in April 2006. What is the latest
it can start work before the wet season starts?
The southern extension to the test pit is important for maintaining operations
past the next wet season. The commencement of civil works is contingent
on Government approval. Depending on if and when this is granted we will
then amend our development schedule.
What are the mine's power requirements and how will these change?
At present, the mine requires about 18 MW of power, the majority of which
is used in the mill. There will be no change in the operation's power
demand. Power will continue to be generated by the existing on-site gas-fired
power station.
Who owns MRM?
MRM is wholly owned by Xstrata Zinc. In September 2005, Xstrata acquired
the 25% interest in McArthur River Mining previously held by a joint venture
partner - ANT Minerals Pty Ltd.
What is the extent of deposits at the mine?
The McArthur River ore body remains one of the largest known deposits
of zinc and lead in the world, with a measured and indicated ore resource
of greater than 120 million tonnes. The proposed development would mine
identified reserves of 43 million tonnes containing 11.9% zinc. 5.2% lead
and 53 g/t silver.
What is unique about the MRM deposit?
Due to the fine grained nature of the deposit, the ore must be milled
extremely finely (<10 microns) to free the valuable metals from the
waste rock. Even at this fine grind, MRM can produce only a bulk concentrate.
Imperial Smelters (ISP's) are the primary market for the bulk concentrate
produced at MRM.
back to top
2. Environment
How will the mine site footprint change?
The major elements of the footprint of the existing mine are the surface
processing facilities, the tailings storage facility, the accommodation
camp and the airstrip. They occupy an area of about 12 square kilometres.
The open cut project will add the following additional components to
the existing footprint, which will increase its area by about 12 square
kilometres to include:
The land required is within the current mining lease area and no new
land is needed for the change of operation.
What will be the impact of rechannelling the McArthur River?
McArthur River flows for 300 kilometres. The 5.5 kilometre section being
rechannelled accounts for about 1.6 per cent of the river. The river is
actually an intermittently running or dry creek much of the year, with
several permanent waterholes near the mine. During the Wet season, the
river sometimes floods (three times in the past 10 years) and can be as
wide as 15 kilometres.
The realigned channel will be designed to have similar hydraulic characteristics
to the existing river channel so it is stable during floods. The lower
channel bank will be stabilised against erosion and the banks and berms
will be revegetated. This will minimise the risk of erosion and allow
the riverine fauna corridor to re-establish.
Construction will be over two years, to help vegetation re-establish.
There may be some extra silt in the first year's wet season but modelling
suggests no long-term impact on water quality, flora or fauna. Part of
the rechannelling follows an old watercourse. After about 20 years, the
riverine environment should have been recreated.
What impact will this have on the floodplains, especially during the
wet season?
Floods less than 1 in 5 year levels will be contained within the realigned
channel. Floods greater than one in five years will extend over the McArthur
River floodplain as happens at present.
The presence of the mine will result in increased flood water levels
upstream of the mine (eg levels will increase by 1.4 metres for a 1 in
100 year flood). This increase will not have any adverse environmental
effects but will increase the extent and duration of upstream flooding.
The only significant impact will be on the Carpentaria Highway, which
closes now during severe flooding. The highway's closure times will increase.
What will be the impact on fish generally and threatened species such
as the Freshwater Sawfish?
The realigned river channel will be designed so there is no physical
or hydraulic obstruction to fish passage. A variety of substrates and
micro habitats will be provided along the channel to minimise impacts
on fish. A comprehensive monitoring program for the Freshwater Sawfish
is proposed.
How will the open pit be protected from flooding during the wet season?
The flood protection bund has been designed to keep flood waters out
of the open cut. It will be high enough to retain the 1 in 500 year flood
and will have a central clay core to provide an impervious barrier to
water. The outside wall will be lined with rock to provide protection
against erosion and scouring of flood waters.
What will happen to the Glyde River during this project?
The open cut project will not have any impact on the Glyde River as it
is no longer part of the project area.
What impact has the existing tailings dam had on the environment?
Waste water and solids from the MRM processing plant are taken by pipeline
to the nearby tailings dam, where water is recycled and solids are stockpiled.
The tailings dam has experienced some minor sulphate seepage, similar
to salt deposits, into Surprise Creek. The creek runs for only a limited
number of days each year. Close monitoring of the seepage area, analysing
samples taken from the creek on a weekly basis as long as water is accessible,
has shown that no heavy metals have entered Surprise Creek. Monitoring
of flora and fauna in the area surrounding the tailings dam has equally
recorded no impact on local flora or fauna.
MRM has worked to eliminate this seepage in a number of ways, including
a trial involving injecting polymer fill along 750 metres of the most
affected area. This successful trial led to a major AUD2 million project
to apply the treatment to 1.5 kilometres of the tailings dam wall which
was completed in September 2005.
The tailings dam will also be extended away from Surprise Creek as part
of the move to open cut mining and new deposits will be placed in cells
furthest away from Surprise Creek. Cells nearest Surprise Creek will be
rehabilitated to prevent any further seepage.
What impact will the open pit have on groundwater systems?
A system of groundwater extraction bores will be built around the open
pit to prevent groundwater flowing into the pit, which would interfere
with mining activities. The extracted groundwater will be used as process
water in the process plant.
Extracting the groundwater will cause groundwater levels surrounding
the pit to drop. At the end of the mine's life, groundwater levels could
have dropped by up to 35cm if no action is taken to manage it. MRM is
looking into ways to make sure there is no draw down and will be regularly
monitoring and measuring groundwater levels.
Even without mining, groundwater levels in the area fluctuate naturally
by up to six metres between the wet and dry season. Once mining has stopped,
groundwater will return to its pre-mining levels.
Will the project impact on the marine environment?
The marine environment has been annually monitored since 1992, three
years before mining started in 1995. All of these studies show there has
been no environmental harm caused by mining operations.
There will be no changes to the port facilities or marine operations
as part of the open cut development.
MRM has already committed to expand its marine monitoring program to
even more closely track the health of the flora and fauna as well as water
quality and sediments.
For further information, refer to Factsheet
5: Riverine and Marine Environment.
What is the impact of the test pit?
The two stages of the test pit occupy a 12.4 hectare footprint and are
located near the existing mine facilities and between Barney Hill and
McArthur River. This is an area that is already partly disturbed and it
will be mined using conventional open pit methods.
An archaeologist was been commissioned by MRM to ensure that no archaeological
sites were disturbed during the construction of the test pit without assessment
and approval under the Northern Territory Heritage Conservation Act 1991.
The two stages of the test pit were approved after MRM satisfied the
NT Office of Environment on our action to address a range of environmental
and social issues. For example:
Potentially acid-forming overburden material was placed underground
as backfill;
Wet season surface water inflows are controlled with a bund wall around
the pit;
Haul roads and access roads are contoured and bunded to direct run-off
water via sediment containment structures;
Noise and blasting restrictions depend on weather conditions and the
interaction with underground operations;
Water trucks are used to minimise dust generation;
Monitoring programs were expanded to cover dust and water monitoring.
What impact will the project have on carbon dioxide emissions?
The annual greenhouse gas emissions from MRM will increase marginally
from 117,900 tonnes of carbon dioxide (equivalent) in 2004 to 124,100
tonnes in 2008. This small rise results from the increased tonnage of
ore mined from 1.6 million tonnes to 1.8 million tonnes in order to maintain
the existing concentrate production rate.
What role does the Australian Government have?
The Australian Government has declared that the project is a 'controlled
action' under the provisions of the Environment Protection and Biodiversity
Conservation Act 1999. This means that the Australian Government will
assess the project's EIS and approval will be needed before the project
can start.
The Australian Government review will occur as part of the NT assessment
process under the terms of the Bilateral Agreement between the Australian
and Northern Territory Governments.
What will happen to the mine at the end of its life?
MRM's mine closure strategy that has been approved by the Northern Territory
Government. This strategy will be updated to incorporate the open cut
project. Key elements of the mine closure strategy will include:
-
The river will continue to flow along the realigned river channel.
-
The flood bund will be breached and the open cut allowed to fill
with flood water.
-
The processing plant and infrastructure facilities will be removed
and the areas remediated and revegetated.
-
The overburden emplacement facility and the tailings storage facility
will be topsoiled and revegetated.
-
Rehabilitation will ensure that the final result is a stable, vegetated
landscape which has minimal impact on the surrounding environment.
back to top
3. Social
What benefits does the mine provide to the Northern Territory?
In the past, the mine has contributed about AUD350 million directly and
indirectly to the Northern Territory economy and employed around 350 people.
The change in mining method to open-cut will ensure that approximately
270 jobs are retained at the mine and economic benefits of around AUD329
million continue to be generated.
The mine also works with around 400 suppliers in the Northern Territory
supporting an estimated 1,430 jobs.
What jobs are available to the local community and Indigenous people?
McArthur River Mining's aim is to work with the local school to provide
links between programs that encourage children to get an education and
vocational training that provides long-term skills.
The mine has a pre-employment program, to help local people get work,
and plans to double its current target of 10 trainees a year with the
open cut mine. Over 200 local indigenous people have been employed by
MRM.
What community consultation has taken place?
A community consultation program has been implemented which sought to
capture the views of local residents and relevant organizations. Through
a program of personal meetings, consultation meetings with community groups,
and liaison with community advisers, MRM has maintained a dialogue with
the community. In addition, a series of information sheets, an information
line and this website have been available for further information.
Have traditional owners been consulted?
Traditional owners have been involved in all of the community consultation
activities including several visits to the MRM site to view development
plans and advise on sacred sites.
Are any sacred sites affected?
The Aboriginal Areas Protection Authority (AAPA) has identified 146 sites
in the general McArthur River project area. This includes five registered
sacred sites in the south-west corner of ML 1122 close to the McArthur
River and one south of the mining lease.
The AAPA has issued authority certificates for all of the open cut project
components in accordance with Section 22 of the Northern Territory Aboriginal
Sacred Sites Act 1989. These certificates include special conditions to
protect all sacred sites near the project.
MRM remains committed to ongoing consultation with traditional owners
during the construction and operation of the open cut. AAPA certificate
conditions will be strictly observed to ensure that any sensitive areas
and/or issues are identified and managed to the benefit of all parties.
An archaeologist has been commissioned by MRM to ensure no archaeological
sites are disturbed during the construction of the project without assessment
and approval under the Northern Territory Heritage Conservation Act 1991.
What benefits does the mine deliver to traditional owners?
The mine is on the old McArthur River station. When it opened in 1995,
the Australian Government negotiated directly with Gurdanji traditional
owners, who relinquished title in return for the nearby Bauhinia Station.
An additional recent excision on the mine's land has been made by MRM
for Gurdanji traditional owner Billy Coolibah.
As well as jobs and training, the continued export of concentrate delivers
benefits to the Mawurli and Wirriwangkuma Aboriginal Association (MAWA).
This is an indigenous business enterprise representing the four language
groups in the region and which owns a 32% share in Carpentaria Shipping
Service; a joint venture with P&O. This company operates the barge
from the port of Bing Bong to ocean-going ships. Profits distributed to
MAWA from this company contribute to local cultural, educational and social
benefits.
back to top
4. Public Environmental Report Process
Is this a case of "back to the drawing board" for MRM's open
cut proposal?
No. It is just part of the statutory process under the Environmental
Assessment Act that needs to be followed. The overall project has not
changed.
How long will the 14a process take?
The NT Government is responsible for the process so the timing is up
to them.
14A is usually for altered projects - how is MRM altering its open cut
proposal?
The overall project remains the same in that we still need to divert
the McArthur River in order to move to open cut mining.
The modifications to the project relate to the design of the new river
channel and our environmental monitoring program.
Is there any possibility of switching to open cut without diverting
the river?
The nature of the orebody is that lies underneath the river. There is
no way of accessing it long term without diverting the river.
We are conscious of the environmental concerns this raises but have done
an enormous amount of work with Australian and international experts on
the design of the new river channel.
Should you/Could you have worked harder in the first EIS to convince
NT stakeholders about the need for the river diversion?
The draft EIS lodged in August represented more than two years' work
by leading Australian and international environmental advisers. In hindsight
you can always do more but we were satisfied with the depth of analysis
and scientific evidence our documents provided.
back to top
5. Test Pit Southern Expansion
Why is it called a test pit? What are you testing?
The aim of the first stage of the test pit was to confirm the nature
of the outcrops of ore below the surface and enable metallurgical tests.
All ore generated by the test pit was processed through our concentrator
to ensure it met specifications.
The second stage of the test pit will enable us to continually fine tune
our methods. But the ore produced is important to keep the mine operating.
Isn' this the first stage of your open cut development?
It is a continuation of the Mining Management Plan that governed the
initial test pit. The first stage of the test pit was always intended
for ore sampling and production.
The second stage will allow us to fine tune our methods but the ore produced
is important to keep the mine operating. It will provide security for
our staff, suppliers and customers.
The open cut development is a 25 year plan. This test pit is important
for us short term but it only represents a comparatively small area.
What process did you follow for the approval of the expanded test pit?
MRM submitted a proposal for an update to our Mining Management Plan
(MMP) including a comprehensive environmental report. This was reviewed
by the Department of Primary Industry, Fisheries and Mines and the Environmental
Protection Agency under two Acts the NT Environmental Assessment
Act and the Mining Management Act. The approval was conditional on a security
payment now totalling $25 million to which we agreed.
back to top
6. PER Lodgement Announcement
Is the proposal radically different to what was presented in the EIS?
The overall project remains the same we still need to divert the
McArthur River in order to move to open cut mining. The changes
to the development relate to the design of the new river channel and our
ongoing environmental monitoring program. The PER has taken all
the planning to a greater level of detail.
Has Professor Erskine approved the modified river diversion design?
We have included Professor Erskines recommendations into the amended
design for the river diversion. The PER will be reviewed for approval
by the NT EPA. I expect Professor Erskine will be asked for his
opinion as part of this review.
Is there anything Professor Erskine recommended that was not included
in the design?
There was a series of technical discussions with Prof Erskine and he
visited the site in early June. Through this we have agreed on the accuracy
of models used, strategies for managing river velocity and erosion, revegetation
plans and environmental monitoring.
How extensive have the modifications been to the design?
There are changes in the detail of the design of all aspects of the development.
We have taken our plans a step further to refine the design. The
new technical studies conducted allow us to now be more precise in exactly
what the diversions will look like and how they will be developed.
When you are expecting to get a decision from the NT Government?
This is really up to the Government. Under the 14A process, the community
will have 28 days from today to submit comments and then the NT EPA will
submit its report. The earliest we might have a decision is August.
What happens if you dont get a decision by August?
That would alter our development plan as we would hope to start work
immediately if an approval is granted. We need to do some civil work before
the wet season.
Has the government given any indication that they are keen for the mine
to proceed?
We have to let the assessment process run its course. The NT Government
has a specific process for reviews under the Environmental Assessment
Act and we are following it.
Are you expecting the government to approve the development on the strength
of the PER?
We would hope that we will have a decision either way at the end of this
process.
What would be the consequences if the NT Government rejects the PER?
Will the mine be closed immediately?
The southern extension to the test pit will support our operation until
around March 2007. If the necessary approvals arent granted for
the change in mining method the mine will then be closed and rehabilitated
in accordance with MRMs approved closure plan.
back to top
|